The water line work associated with the Fraser Hall renovation project will begin next week and continue until approximately July 3. Activities include:

  • Installation of fencing to restrict access around the “snake pit” (the island off the southeast corner of OM in Parking Lot 10G)
  • Installation of fencing in the Rose Garden
  • Arrival and operation of dump trucks and excavation equipment
  • Delivery and installation of an ADA ramp on the south side of Humanities

These activities will impact entries to both Old Main and Humanities. Detour signs will re-route pedestrian/vehicular circulation. Equipment operation and fencing installation will create noise and dust.

Please address any questions or concerns to the project manager, David Willett, at 360-650-6813 or david.willett@wwu.edu.

The Humanities exterior renewal project will begin June 17 and continue through the end of summer. Activities include:

  • Installation of fencing around work area
  • Installation of scaffold
  • Washing and cleaning of exterior walls
  • Removal of sealant