Carver Renovation Construction Update
Efforts to enclose Carver before winter continue.
ONGOING IMPACTS
- Pedestrian/vehicular detours remain in place.
- Contractor continues to mitigate noise, dust and other construction impacts as much as possible.
- Welding activities are shielded where possible.
REMAINING WEEKS OF DECEMBER
- Continue installation of interior mechanical and electrical systems
- Continue interior wall framing and installation
- Continue interior painting
- Continue roofing
- Continue door framing
- Continue exterior masonry restoration and brick masonry on exterior 1959 building
- Continue to install glass curtain walls; multiple cranes on site
- Continue rough site grading and installation of storm water branch lines
- Begin ceramic tile installation in showers and locker rooms.
- Begin acoustical spray for gym ceiling
- Begin 1935 window installation
If you have any concerns or questions, please contact Dale Krause, construction coordinator at 360-650-4646 or dale.krause@wwu.edu.