Carver construction update: weeks of Feb. 21 and 28
Carver construction activities for the week of Feb. 21:
- Continue abatement/demolition roof in 1960 buildings.
- Continue excavation for building foundation. Excavation work under Gym A will create noise and vibrations that may impact Bond Hall.
- Continue underground plumbing work.
- Continue underground electrical work.
- Continue grading and concrete pouring. Expect back-up beeper noise from trucks.
- Continue structural interior work in Gyms A, B and C.
Carver construction activities for the week of Feb. 28:
- Continue abatement/demolition roof in 1960 buildings.
- Continue excavation for building foundation. Excavation work under Gym A will create noise and vibrations that may impact Bond Hall.
- Continue underground plumbing work.
- Continue underground electrical work.
- Continue grading and concrete pouring. Expect back-up beeper noise from concrete pump and concrete ready-mixed trucks at the north end of the construction site.
- Continue structural interior work in Gyms A, B and C.
For more information, contact Dale Krause, construction coordinator at 360-650-4646 or dale.krause@wwu.edu.