Carver construction update: 10/3/16
IMPACTS
- Pedestrian/vehicular detours remain in place.
- Contractor continues to mitigate noise, dust and other construction impacts as much as possible.
- Welding activities are shielded where possible.
WEEKS OF OCT. 3 & 10
- Continue installation of interior mechanical and electrical systems
- Continue taping, mudding, sanding and hanging dry wall
- Continue painting
- Continue roofing
- Continue wall and door framing
- Continue cleaning exterior masonry
- Install glass curtain wall on central bar; crane on the north side will lift panels in place
- Begin rough site grading
- Apply a sealer to gym ceilings in preparation for spraying acoustical insulation. Spray application of the sealer may create odors that may drift beyond the construction site.
For questions/concerns, please contact Dale Krause, construction coordinator, 360-650-4646 or dale.krause@wwu.edu.