Carver construction: Town Hall info now posted

Information distributed at last week’s Carver Renovation Town Hall Meeting is now posted online.

Construction activities this week include:

  • Finish demolition of central corridor; grade and fill.
  • Finish demolition of Gym C and east entry.
  • Continue demolition of Gym B.
  • Begin demolition of Gym A.
  • Continue storm sewer site work.
  • Crews will work 10-hour shifts, from 7 a.m. to 5:30 p.m., Monday through Friday.
  • Concrete breaker to be used intermittently throughout the week.

Next week’s activities will include:

  • Continue demolition of Gym B.
  • Finish demolition of Gym A.
  • Continue grading and filling central corridor.
  • Continue storm sewer site work.
  • Expect continuation of the noise, dust, truck traffic and vibrations.

For more information or to share concerns, contact Dale Krause, construction coordinator, at 360-650-4646 or dale.krause@wwu.edu.