Electrical shutdown in the Comms Facility set for March 26-27

To accommodate the Banner upgrades scheduled for March 28 and 29, the electrical shutdown in the Communications Facility has been rescheduled to begin Tuesday, March 26 at 4 p.m. and finish on Wednesday, March 27 at 10 a.m. 

Normal electrical power to the building will be shut down to allow the connection of Kaiser Borsari Hall to the campus power system. The entire building will be without power for outlets, elevators, heating, ventilation, and lighting. Fire alarms and emergency lighting will continue to function.

Building occupants should plan to work remotely if possible.

Please direct any questions to:

Mark Nicasio, Project Manager Architect

(360) 650-6296